Date: March 19, 2026 Pre-Construction and Plan Review
Date: April 1, 2026 Review, verify and ensure a shared understanding of the house plans, structural options and where the house will be placed on the lot. Other items addressed include:
As in every meeting, go over site safety requirements, explain the construction schedule and any potential revisions or delays and establish the schedule for upcoming meetings and estimated completion dates. Pre-Slab Orientation
Date: TBD This meeting is scheduled once the building permit is received. Progress has been made with the scraping of the lot, form boards will be in place to show the orientation of the garage, the footings and foundation can be seen, preparation for any structural options, underground plumbing and electrical and the steel rebars that hold it all together. Lintel/Block Orientation
Date: TBD This is an opportunity to see the strucural integrity of the house - block walls, hurricane strapping, reinforcing steel and continuous load path construction. It's a review and confirm window and door locations and options such as sliders, floor outlets and hose bibs. Review the construction schedule and any potential revisions or delays and establish the schedule for upcoming meetings. Pre-Drywall Orientation
Date: June 16, 2026 All strucural selections are in place and can observe behind the walls, such as:
Review the construction schedule and any potential revisions or delays and establish the schedule for upcoming meetings. Cabinet and Countertop Orientation
Date: August 20, 2026 This meeting is approximately 3-4 weeks after the pre-drywall orientation to ensure cabinets are as selected. It's to confirm the correct installation of cabinet style, color, personalized designs and hardware. Countertops will be installed as well. Review the construction schedule and any potential revisions or delays and establish the schedule for upcoming meetings. Grading Orientation
Date: TBD The purpose of this meeting is to walk around the house to see landscape beds and irrigation, tree placement, and property line boundaries. The construction manager will explain what effect fences will have on drainage. Review the drainage plan and where and how the lot will drain. Note: the lot will drain completely within 48 hours. Review the construction schedule and any potential revisions or delays and establish the schedule for upcoming meetings. Pre-Closing Orientation
Date: October 6, 2026 This meeting is about 1 week before closing. A great deal is covered through demonstration and detailed explanation:
Any exceptions will be documented as the punch list. Final Walkthrough
Date: October 20, 2026 If there is a punch list, verify and approve completion. Closing
Date: October 21, 2026 Spectrum
Date: October 22, 2026 Five Star Painting
Date: October 22, 2026 Culligan
Date: October 22, 2026 ADT
Date: October 23, 2026 |